pw2pa-alliance-Joy-Baluch-Bridge
Aerial view of the Westside Foreshore (February 2021)
5.-Aerial-View-of-the-Eastside-Foreshore-and-the-Project-Construction-Site-(May-2021)
8.-Aerial-View-of-the-Westside-Foreshore-and-Marine-Section-of-the-Bridge-under-Construction-(June-2021)

Joy Baluch AM Bridge Duplication

Project Overview

The Australian and South Australian governments have committed $200 million ($160 million from the Australian Government and $40 million from the South Australian Government) for the Joy Baluch AM Bridge Duplication Project.

The Joy Baluch AM Bridge is an important link in the National Land Transport Network at Port Augusta, providing access across the Spencer Gulf for commuter, commercial and freight vehicles in the northern region of South Australia. It is also a key tourist connection to the Eyre Peninsula, northern South Australia and beyond.

The duplication of the bridge is improving road safety, freight productivity and efficiency for all road users.

The project involves the construction of a new bridge, adjacent the existing two-lane Joy Baluch AM Bridge, to allow for two lanes of traffic in both directions between Mackay Street (east of the bridge) and Burgoyne Street (west of the bridge), and upgrades to pedestrian and cyclist facilities, with connectivity provided from the new bridge to the Eastside Foreshore. Further works include:

  • upgrade to the intersection at Mackay Street and Augusta Highway, including traffic signals and new pavements;
  • remediation and strengthening to both the existing Joy Baluch AM Bridge and the bridge over the ARTC rail corridor between Flinders Street and Mackay Street;
  • widening of the existing embankments from Tassie Street to the west of Flinders Terrace to accommodate new lanes and a shared path facility; and
  • new connections for pedestrians and cyclists from Mill Street and Tassie Street to the Mackay Street intersection, and removal of the existing spiral staircase on the Eastside Foreshore.

As part of the delivery of urban design elements and artworks for the project, the Alliance has been collaborating with Aboriginal stakeholder groups, Port Augusta City Council and other key stakeholders in the design and implementation of cultural elements to strengthen local identity, cultural respect and interpretation of place.

On 15 May 2022, the newly constructed bridge opened to traffic, with all vehicles directed to use the new bridge to allow for the remediation of the existing Joy Baluch AM Bridge. 

Another significant milestone was achieved on the project on 6 June 2023, when two lanes of traffic opened in each direction on the Joy Baluch AM Bridge, and signalised Mackay Street intersection became operational.

Some intermittent lane and speed restrictions will continue to be required for finishing works, ahead of the project’s full completion in 2024.

Additional project information can be found on the Department for Infrastructure and Transport’s website: Joy Baluch AM Bridge Duplication – Department for Infrastructure and Transport – South Australia (dit.sa.gov.au)

Timeline

Activity
Estimated Date
Geotechnical testing
Completed
Site establishment
Completed
Early works
Completed
Final design (excluding urban design aspects)
Completed
Construction of the new Joy Baluch AM Bridge
Completed
New Joy Baluch AM Bridge opening to traffic
Completed
Refurbishment of the existing Joy Baluch AM Bridge
Completed
Finishing works
In progress
Full project completion
2024

Project Updates

November 2023

October 2022

September 2021

April 2021

October 2020

July 2020

Works Notices

Changed Traffic - Joy Baluch AM Bridge - Night Works Dec 2024 - updated

Changed Traffic - Augusta Highway - November 2024 - updated

Changed Traffic Arrangements - Augusta Highway - September 2024

Carpenters Landing boat ramp restrictions - September 2024

Changed Traffic Arrangements - Augusta Highway - July 2024

Temporary Road Closure - Tassie Street - June 2024

Changed Traffic Arrangements - Augusta Highway - August 2023

Changed Traffic Arrangements - Augusta Highway - June 2023

Augusta Highway Night Works Notice - April 2023

Changed Traffic Arrangements - Augusta Highway - March 2023

Changed Traffic Arrangements - Augusta Highway - January 2023

New Pedestrian Access to Tassie Street and CBD - December 2022

Changed Traffic Arrangements - Augusta Highway - September 2022

Mildred Street Closure Notice - August 2022

Mackay Street and Tassie Street Traffic Changes Notice - July 2022

Traffic Switch to the New Bridge Notice - May 2022

Augusta Highway Night Works Notice - March 2022

Augusta Highway Traffic Restrictions Notice - November 2021

Temporary Langsford Street Closure Notice - September 2021

Traffic Restrictions Notice - August 2021

Read More

Extended Temporary Tassie Street Closure Notice - June 2021

Night Works Notice - June 2021

Night Works Notice - Intermittent Traffic Restrictions - June 2021

Augusta Highway Traffic Restrictions Notice - May 2021

Southbound Lane Intermittent Restrictions Notice - April 2021

Temporary Tassie Street Closure Notice - March 2021

Marine Exclusion Area Notice - January 2021

Marine Piling Notice - January 2021

Fact Sheets

Road Construction - What's Below the Surface?

Piling Works

Managing Construction Impacts - Environmental Management

Managing Construction Impacts - Marine Fauna

Presentations

Regional Development Australia Far North - PW2PA Economic Forum Presentation - March 2023

Designs and Artist Impressions

Read More

News

<strong>PW2PA Alliance Projects Improving Freight Network</strong>

PW2PA Alliance Projects Improving Freight Network

In June 2023, the Joy Baluch AM Bridge in Port Augusta opened fully to two-lane,…
Key milestone switched on for bridge duplication project

Key milestone switched on for bridge duplication project

Wednesday, 7 June 2023 The Joy Baluch AM Bridge in Port Augusta is now operating…
Celebrating Steps on the Career Path

Celebrating Steps on the Career Path

Edwin Davey, General Superintendent, PW2PA Alliance, at centre with the latest group of graduates. On…

Joy Baluch AM Bridge Community Event

The PW2PA Alliance invites you to walk over the newly refurbished Joy Baluch AM Bridge…

Fast Facts

$200M

$200 million Joy Baluch AM Bridge Duplication Project jointly funded by the Australian and South Australian governments

Benefits

Improved safety for all road users
Improved efficiency
Improved freight productivity

Walking Paths

Dedicated Shared Use Path from the Westside Foreshore to Flinders Terrace

Materials

132 bridge beams
46 steel piles
439 concrete barriers
30,000m3 of earthworks

Vehicle Use

17,600 vehicles per day

761b WuStrasse Burste, Amsterdam, NL